Before-dispatch document guide

Steel Pre-Shipment Document Check

A certificate can describe the right grade yet belong to the wrong heat or package. Before dispatch, match each accepted PO line to its material record, packing-list line and proposed package marks. Keep discrepancies open until an authorized person resolves them.

Chat on WhatsApp
01 · Governing order

Start With the Latest Accepted PO Line

Use the accepted PO and any approved amendment as the comparison point. Record the line number, grade, product form, standard and edition, dimensions, finish or coating, quantity, required inspection-document type and drawing revision. Add the named delivery rule and destination only where the order specifies them. Ask which version the sourcing and logistics contacts are using; an old quotation, a draft change or a later email is not automatically the governing line. For a multi-line order, make a separate row for each size or grade so that a correct total weight cannot conceal a wrong individual line. Name the person who can approve a deviation before documents are checked.

  • IdentifyPO number, accepted revision and line number.
  • SpecifyMaterial, form, size, condition and agreed document type.
  • AuthorizeName the order or quality contact who can resolve a difference.
02 · Material identity

Tie the Material Record to the Proposed Goods

If an inspection document is required, check its stated material grade, product form, specification, edition, size, test unit and heat or lot identifier against the accepted PO line. Then ask how that heat or lot identifier will appear on the packing list and physical package mark. The purchase order must state the inspection-document type required for this transaction. A report with plausible chemistry is not evidence for a package whose identity cannot be linked to it. Document review also does not prove that a physical inspection took place. Use the separate certificate-reading guide to interpret individual test fields; this page stays focused on whether the document belongs to the proposed shipment.

CompareCheckUnresolved if
PO lineAccepted grade, standard, form and sizeDocument names a different line or revision
Material recordRequired type and heat or lotRecord is absent or identity cannot be tied to goods
Package markSame identifier as the proposed materialLabel points to another heat or is unreadable
03 · Four-way match

Reconcile the Packing List With Package Marks

Ask for a packing-list row for each PO line and package group. Compare form, size, piece or bundle count, coil count where applicable, stated weight basis and package identifiers with the material document. For sheets, tubes and bars, a piece or bundle mark may matter more than a coil number; do not force coil fields onto every form. If the contract calls for label photographs, ask that the photo show the actual identifier and enough context to locate the package. A photograph supplied for discussion is not automatically proof that the goods were independently inspected. Keep a discrepancy column so you can see exactly which package or line needs correction before release.

PO lineMaterial recordPacking-list rowProposed package markAction
Accepted grade, form, size, quantityRequired type and heat/lotPackage count, size and IDReadable corresponding IDMatch or record discrepancy
Quote request

Have a Specification Ready?

Send what you already know, such as grade, finish, size or quantity. Inquiries are answered within 2 hours.

Chat on WhatsApp
04 · Document purposes

Keep Shipping Papers Separate From Material Proof

A commercial invoice, packing list, transport document and any origin or destination paperwork address commercial or logistics requirements. An MTC or other agreed inspection record addresses the material information stated in that document. One does not replace the other. List the exact papers you need under the contract, destination rules and named Incoterms rule, then identify who must issue each and when it must be ready. The ICC description of Incoterms provides the trade-rule framework; it does not create a universal document bundle for every steel shipment. Ask ZIVO to confirm order-specific availability with the supplying route instead of assuming that every certificate, photo set or third-party report is included.

Document purposeWhat to confirm
Material identityAgreed test record, heat or lot, and link to package marks
Commercial termsInvoice fields and contract details needed for the order
Movement and destinationTransport, origin or other papers explicitly required for this shipment
05 · Hold or release

Resolve Exceptions Before Authorizing Dispatch

Give each difference an affected PO line and package ID, a description, the current evidence, a correction owner and an approval owner. A missing required certificate, heat number that does not match a label, quantity disagreement or superseded PO revision should remain open for a corrected record or an explicitly approved deviation. If you need a physical witness or third-party inspection, agree its scope and timing for the actual order before dispatch; desk review cannot replace it. Record who may release the affected line, and tell the receiving team which final version they should use. This is a decision workflow, not a claim that ZIVO operates an automatic dispatch hold for every order.

ExceptionEvidence to requestRelease decision
Wrong or missing heat/lot linkCorrected traceable record and package markHold affected line until authorized resolution
Superseded PO revisionAccepted amendment and matching shipment packetUse the approved final version
Quantity or package count differsCorrected line and count explanationRecord the agreed disposition
06 · Request packet

Send One Checkable Pre-Dispatch Request

Send the accepted PO revision and per-line specification, the required inspection-document type, heat or lot and marking requirements, a packing-list layout, any agreed label-photo request, and the destination and named delivery rule. Add the commercial papers actually required for the transaction, the deadline for review and a contact who can decide discrepancies. Ask for an order-specific response showing what can be provided, by whom and at what stage. Do not assume fixed turnaround or a universal pre-shipment photo service. Keep the final accepted packet for the warehouse so receipt checks use the same material and document identity.

  • OrderAccepted PO line, revision and material description.
  • TraceRequired document type, heat/lot and package-marking plan.
  • DecisionDocument deadline and named exception approver.

Frequently Asked Questions

Get a quotation

Tell Us What You Need

Send the product form, grade, finish, thickness, width, length and quantity. Inquiries are answered within 2 hours.

Chat on WhatsApp
Send Inquiry

Request a pre-shipment document check

Share the accepted PO line and revision, material and inspection-document requirements, marking and packing-list expectations, destination and decision contact. ZIVO can confirm the order-specific document and inspection arrangements with its sourcing route.

Tell us what steel you need. You can include the grade, size, quantity or intended use if available.

Inquiries are answered within 2 hours.